April 27, 2024

Short-Circuiting the High Cost of Transformer Upgrades

by Alan Ober

Increase capacity! When the call comes from upper management to produce more energy, a plant manager faces the challenge of upgrading the infrastructure, and upgraded power transformers often represent the biggest ticket item.

Adding to the expense is the fact that such change-outs usually require completely reworking the connections to and from the transformer. When spatial constraints that require rebuilding a new enclosure or pad mount are factored in, the prospect of increasing capacity can explode into a budget-busting endeavor.

In response, many plant managers are discovering the advantages of new retrofit transformers. These fully customized power transformers provide the benefits of increased power capacity while duplicating the form and fit of the originals. The option of a perfectly matched, plug-and-play transformer holds the potential for capacity upgrades that meet regulations, timelines and budgets.

The experience of one major power utility demonstrates that plant managers can successfully balance the demand for upgrades against the cost constraints set by the controller by retrofitting.



Saving Money in the “Show Me” State

Since “first fire” more than 40 years ago, management at Ameren Missouri’s Rush Island Energy Center in Festus, Missouri, has run a tight ship. The plant’s two, coal-fired generating units have often scored one and two in the nation for the lowest NOx produced by units without selective catalytic reduction, while producing 1,242 megawatts of electricity.

Here, the impetus for transformer upgrade stemmed from a larger project that required more power for added in-house load.

“We were upgrading our bottom ash system, changing from a wet sluicing system with bottom-ash clinker grinders to a submerged flight conveyor, and the existing auxiliary boiler stood in the way of the conveyor,” explained Herb Fischer, consulting engineer, Rush Island technical support. “So, we demolished the old ‘aux’ boiler and put in a new one.”
 



The jump from 75 to 250 horsepower needed for the forced draft fan on that boiler drove the need for the larger transformers. The load study called for upgrading the supply transformers from 1000 kVA to 1300 kVA.

On the face of it, ordering bigger transformers with larger secondary windings would seem simple enough, except that Fischer and his team faced the difficulty of having to fit the new transformers into an existing cabinet with no leeway for extra girth. Rebuilding the enclosure and reworking the terminations would have pushed back the project deadline and led to a large cost overrun.

“There were several components involved in making a decision for the replacements, and cost and fit were high on the list,” continued Fischer. “For those reasons, we had to have a supplier that could handle this type of custom work with a quick turn.”

The project took place at a double-ended unit substation within the energy center and only four days were allotted for the complete removal of the old transformers and the installation of the two 6900V to 480V replacements.

“The enclosure was going to stay so the dimensions had to fit and the transformers had to match up with the high voltage connection and the low voltage bus bar,” said Fischer. “Not having to perform any field modifications was critical, so only a duplicate retrofit would do.”

Retrofit Explained

Retrofit transformers represent significant cost savings for plant managers seeking to reduce capital expenses primarily because of the plug-and-play advantage of a perfect fit. Yet, without proper manufacturing controls, performance and reliability could end up sacrificed.

When it comes to the material used in the windings of a well-manufactured retrofit, copper is a superior conductor to aluminum because copper offers less resistance, hence less heat. Even the geometry of the windings makes a difference, with round-wound holding the advantage.

Attention to detail also pays dividends in the retrofit manufacturing process. Hand wiring yields the highest quality. Additionally, the deburring of the copper conductor helps ensure that the insulation won’t be punctured and create a short circuit.

Even insulation plays a major part in ensuring reliability. As temperatures can reach 200 degrees C in a dry trans¬former on a daily basis, skimping on insulation can lead to disastrous consequences. Glastic fiberglass insulation or Nomex® provide significantly greater protection from fires and short circuits than paper insulation.

Since Ameren specified a quality dry-type transformer that incorporated all the characteristics of a well-manufactured retrofit, the manufacturer was able to pass along a three-year warranty instead of the industry standard one year.
 



A Fast and Smooth Upgrade at Rush Island

According to the DOE, June 2012 study entitled Large Power Transformers and the U.S. Electric Grid, “In 2010, the average lead time between a customer’s large power transformer order and the date of delivery ranged from five to 12 months for domestic producers.”

Too long. Aside from having to meet the stage gates for any project, the window for an outage must compete with other projects. Miss it, and rescheduling can delay implementation for weeks and quickly inflate costs as contractors sit idle.

For the Rush Island transformer upgrade, the window was Columbus Day weekend of 2017. Retrofitting allowed them to complete the job within the approved timeframe.

“An electrical contractor did the work and had no installation issues whatsoever,” added Fischer. “The bus bars were where they needed to be and the cabling supplied was a sufficient length to reach the existing terminations. It fit like a glove.”

After implementation, Rush Island ordered two more units that also had to be delivered on a short timeline, this time with different voltages. To date, the utility reports it has had no issues with any of the transformers and that everything is functioning to specifications.
 

Alan Ober is the chief engineer at Electric Service Company (ELSCO Transformers), with more than 40 years of experience in the design and manufacturing of transformers.